Construction and installation work on the Tobolsk-Polymer site is 50% complete

Currently, work continues on the propane dehydrogenation site, the polypropylene site, and the utility facilities. Coverings have been erected in the winter over the main work fronts in order to support the project's schedule completion rates. Fan heaters are being used for warmth.

More than 4,000 workers from contracting organisations are engaged in building the complex.

All of the heavy engineering equipment has now been delivered to the construction site. Material support for the propane dehydrogenation plants and polypropylene production plants is more than 99% complete. The detailed design is entirely complete. The strategy for testing and commissioning has been defined and preparations to implement these have begun.